Tienen, Belgium
Raffinerie Tirlemontoise S.A. – Tiense Suikderrraffinaderij N.V.
Location
Refinery
2020
BMA is awarded contract.
2022 - 2023
Delivery and assembly.
2023
Start of commissioning.
- Extraction plant
- Countercurrent cossette mixer
- Extraction tower
- Steel structure
- Piping
- Electrics
- Engineering
- Assembly of the plant
- Electrics
- Piping
- Assembly supervision
- Commissioning
Technical Data
Capacity of the extraction plant | 14,500 t/d |
Upgrade possible | to 17,000 t/d |
Countercurrent cossette mixer | Ø. 7.5 m, length 9.5 m |
Extraction tower | Ø 12.0 m, extraction length 25.38 m |
Annual reduction of CO2 emissions | 6,000 t |
Water saving s | 150,000 m3 |
Facts
BMA supplied and assembled the entire extraction plant as a turnkey solution.